EVALUATION YEAR 1998 PERFORMANCE AGREEMENT
    
PURPOSE OF THIS AGREEMENT

     The purpose of this performance agreement between the Office of Surface Mining
     Reclamation and Enforcement (OSM), Birmingham Field Office (BFO), and the
     Alabama Surface Mining Commission (ASMC) is to:

          1.  Assure the continued constructive relationship currently held by the BFO
          and the ASMC in a shared commitment to accomplish the respective goals of
          the State and Federal Surface Mining Control and Reclamation Act (SMCRA).

          2.  Identify shared goals and work as partners to accomplish those goals
          ensuring that both parties understand their responsibilities for achieving them.

          3.  Identify specific evaluation topics for Evaluation Year (EY) 1998 review.

          4.  Emphasize that overall reclamation success and on-the-ground results will
          be utilized as the primary indicators of program performance.

RESPONSIBILITIES AND GOALS

     A.   Shared BFO-ASMC Responsibilities and Goals

          1.  Develop an EY 1998 evaluation plan that identifies topics for review during
          the evaluation year (Attachments A).  Ensure a clear understanding of the
          topics for review, including any joint evaluations, as well as the methodologies
          to be utilized.

          2.  Establish program areas targeted for special emphasis during EY-1998
          where the evaluation of the target areas will be conducted jointly by both the
          BFO and the ASMC.  ASMC will have the opportunity to participate in other
          oversight studies or surveys conducted during the evaluation year as it may
          choose to do so.

          3.  Promptly address and discuss implementation issues and problems
          identified during the evaluation year in a manner that produces clear
          descriptions of those problems and issues and leads to solutions which are
          mutually agreeable to both the BFO and the ASMC.

          4.  Conduct joint OSM-ASMC inspections for all complete OSM inspections
          to be made during the evaluation year.
          
          5.  Meet at least quarterly to discuss data collection procedures and progress
          and to resolve any outstanding concerns.

          6.  Recognizing that the regulatory program is quite dynamic and that changes
          are often dictated by field conditions, revisions in regulations, policies, etc.,
          this document is subject to modification pending joint ASMC/BFO consensus. 
          Either party may initiate dialogue which results in modifications to this
          performance agreement so long as both parties agree to the modifications.

     
     B.   Birmingham Field Office Responsibilities and Goals

          1.  Serve as the initial OSM source for technical and policy information
          relating to the implementation of SMCRA, responding to all ASMC requests
          for assistance or information in an accurate and timely manner.

          2.  Provide to ASMC the most current technical and policy information. 

          3.  Perform evaluation functions in a fair and open manner with the full
          cooperation of ASMC.

          4.  Immediately notify ASMC of issues that reflect on performance and
          provide adequate time for response.
                              
          5.  If violations of the State's program are encountered during BFO field
          inspections, the State will be notified of the violation through the Ten-Day
          Notice process or, in the case of joint inspections, will be given the opportunity
          to address the violation onsite.

          6.  The BFO will develop an outreach plan to solicit comments from the public
          and interested parties.  Input from the ASMC will be solicited at appropriate
          intervals during the plan implementation.

     C.   ASMC Responsibilities and Goals

          1.  Continue transmitting, to the BFO, program data relating to permitting,
          inspection, enforcement and bonding, in the agreed upon format and will
          continue the computerized transmission of the program data from ASMC to
          the BFO.

     

          2.  Provide data as reasonably determined necessary for the BFO to complete
          reporting requirements pursuant to Directive REG-8.

          3.  Take timely action to resolve all issues and problems identified in EY 1998.

     D.   Non-evaluative Data Collection

          The Birmingham Field Office with the cooperation of the ASMC will gather
          the data listed below for the evaluation year.  The data will not be utilized for
          evaluation purposes, but collection is necessary for the OSM's interactions
          with Congress and with other customers and stakeholders.

               Number of State inspections by type - both complete and partial
               Number of State enforcement actions by type
               Actions concerning lands unsuitable petitions

SIGNATURES

Representing the Alabama Surface Mining Commission and the Office of Surface Mining
Reclamation and Enforcement, Birmingham Field Office, the following parties agree to the
purpose, goals and anticipated actions proposed in this performance agreement.



 /s/ Randall C. Johnson  9/10/97             /s/ Arthur W. Abbs            9/4/97    
Randall C. Johnson,       Date               Arthur W. Abbs                   Date
Director                                                Field Office Director

Alabama Surface Mining Commission       Birmingham Field Office
                                                              Office of Surface Mining
                                                              Reclamation and Enforcement



ATTACHMENT A Alabama Enhancement and Performance Review Evaluation Year 1998 Principle Being Evaluated: Bond Release Reason for Selection: This area is considered for review because of the Directive REG-8 requirement to study the State's effectiveness in ensuring successful reclamation on lands affected by surface coal operations. Requirements: Directive REG-8 states that success in ensuring successful reclamation "will be determined based on the number of acres that meet the bond release standards". Background: Various aspects of ASMC's bond release procedures have been reviewed during the previous evaluation periods. Past studies have shown that all bond release standards were met, bond amounts were properly recalculated, and the state's decisions on awarding bond release request were appropriate in all cases. The 1996 Bond Release Review determined that ASMC was meeting the requirements of its program with regard to bond release and timely reclamation. Population/Sample: An appropriate sample, not to exceed 50 (including Phase I, II, and III releases) will be drawn from releases received by the BFO from October 1, 1997, through June 30, 1998. ASMC will submit the bond release document with the ASMC's Director's initial signature to the BFO (this will allow the BFO approximately 30 days to review these sites prior to the ASMC's Director's final signature). Site reviews will be conducted to evaluate the following parameters: Phase I - AOC achievement, drainage control, land stability Phase II - replacement of soil resources, vegetation stability Phase III - postmining land uses, successful revegetation, surface water quality and quantity, restoration of ground water recharge capacity, comparison of premining to postmining surface water quality and quantity restoration. Summary of Planned Review: Each site visited will be evaluated for the parameters listed above based on the type of bond release under review. Bond release-related documents will be reviewed at the State office to determine the presence of State documentation of the successful completion of these parameters. Success will be based on the number of acres bond released that is in compliance with State performance standards. Reporting: A report of the review will be prepared, and a draft copy will be provided to ASMC for their consideration. Schedule: Commence site reviews in October 1997. Complete data collection by August 1, 1998. Prepare draft report by August 15, 1998. ASMC will routinely be afforded 30 days to provide written comments to the BFO. In the rare instance that a quicker review is needed, it will be specifically requested. ASMC comments will be incorporated, and the final report prepared by September 20, 1998.

ALABAMA ENHANCEMENT AND PERFORMANCE REVIEW EVALUATION YEAR 1998 Principle Being Evaluated: Off-site Impacts Reason for Selection: This area is considered for review because of the Directive Reg-8 requirement to study the State's response to off-site impacts which occur during mining and reclamation activities. Requirements: Directive REG-8 states that "OSM will evaluate and report on the effectiveness of State programs in protecting the environment and public from off-site impacts resulting from surface coal mining and reclamation operations". An off-site impact is normally one that occurs outside the area authorized by the permit for conducting mining and reclamation activities. Off-site impacts affect resources including the people, land, water, and structures. Occurrences of off-site impacts should be noted in Notices of Violation(NOV), except in instances when the impact is not a violation of ASMC's regulations. However the impact should be identified for this review. Background: The BFO began collecting off-site impact data during EY1996 on complete inspections only. As a measurement and reporting of end results, OSM will report nationally in terms of the number and extent of observed off-site impacts. Data collected in this review is not to be used for comparison among States, but rather to identify and to reduce the number of off-site impacts. Population/Sample: All inspections, including those of bond forfeiture sites, performed by OSM during EY1998 will include an evaluation of off-site impacts. The inspections will be performed between October 1, 1997, and August 15, 1998. All associated ASMC inspection reports and documentation during the review year and all citizen complaints which lead to violations during the review year will be reviewed. Additionally, all NOV's issued by ASMC during the period will be evaluated for off-site impacts. Summary of Planned Review: Utilizing Table 4 (Off-Site Impacts) of the Directive REG-8 and a separate data sheet as collection tools, BFO field personnel will collect data concerning off-site impacts during all inspections and the subsequent review of associated ASMC inspections reports and NOV's issued during the period. Positive impacts will also be identified and addressed in the report. Information on impact will also be gathered from State civil penalty assessment records for all violations cited by the State during the review period. Findings will be discussed with ASMC prior to development of the report. Reporting: A report of the review will be prepared identifying the number and degree of off-site impacts, the causes of the impacts, and suggested improvements. A draft copy will be provided to the ASMC for their consideration. Schedule: o Develop an inspection sample, and begin review by October 1997. o Complete collection of data by August 1998. o Prepare a draft report by September 1, 1998. ASMC will be afforded 30 days to provide written comment to the BFO. o ASMC comments will be incorporated, and the final report prepared by October 15, 1998.

ALABAMA ENHANCEMENT AND PERFORMANCE REVIEW EVALUATION YEAR 1998 Principle Being Evaluated: Bond Forfeiture Reclamation Reason for Selection: This area is considered for review in order to evaluate the Regulatory Authority performance with regard to completing the reclamation plan for sites on which the reclamation bond has been forfeited. The measurement will compare ASMC's bond forfeiture site reclamation to applicable standards in the permit reclamation plan. Requirements: Chapter 880-X-9E of the Rules of the Alabama Surface Mining Commission provides for the forfeiture of the reclamation bond as a result of the permittee's failure to meet the conditions of the bond. ASMC can determine the amount of bond funds to be forfeited based on cost estimates, and must use the funds on the permit area on which the bond coverage applies to complete the reclamation plan. Background: The BFO conducted a bond forfeiture review during EY 1995. That review focused on the timely expenditure of collected bond forfeiture funds. The review did not identify any significant problem, but did result in ASMC procedural revisions to enhance the timing and rate of expenditure of bond forfeiture funds and site reclamation. This review will focus on the extent of reclamation compared to the permit reclamation plan. Population/Sample: The population will include all bond forfeiture sites reclaimed since October 1995 as well as all bond forfeiture sites not reclaimed as of October 1, 1997. The sample will include 25% of the sites on which reclamation was completed during that time, and all the sites remaining to be reclaimed. If the sample size is insufficient to complete the evaluation, additional sites may be considered. The sample will include a total of approximately 20 bond forfeiture sites, reclaimed and unreclaimed, on which a field evaluation will be conducted. Summary of Planned Review: The BFO will coordinate each phase of the review with designated ASMC personnel. BFO personnel will review bond forfeiture documents and will discuss with appropriate ASMC personnel to identify ASMC's bond forfeiture reclamation procedures, such as reclamation monitoring. For instance, ASMC's reclamation monitoring procedures for either contractor reclamation or surety reclamation will be evaluated. A field review of bond forfeiture sites will be conducted on the sample sites to evaluate the level of reclamation. Reclamation will be compared to the reclamation plan. Difficulties experienced by ASMC will be addressed. Deviations from the reclamation plan will be noted. Determining factors for reclamation plan revisions, such as land owner consent, necessary reconfiguration, etc. will be reviewed. Reclamation will be also evaluated on the basis of corrections of performance standard violations and achievement of post mine land use. Findings will be discussed with ASMC prior to development of the report. Reporting: A report will be prepared addressing the scope and method of the review, the time frame of the review, samples evaluated or documents reviewed, findings, and recommendations. A draft copy will be provided to the ASMC for their review and comment. Schedule: o Develop an inspection sample, and begin review by January 31, 1998. o Complete collection of data by June 1, 1998. o Prepare a draft report by July 1, 1998. ASMC will be afforded 30 days to provide written comment to the BFO. o ASMC comments will be incorporated, and the final report prepared by August 15, 1998.

ALABAMA ENHANCEMENT AND PERFORMANCE REVIEW EVALUATION YEAR 1998 Principle Being Evaluated: Handling of Citizen Complaints Reason for Selection: This area is considered for review because of the Directive REG-8 requirement to review a sample of specific State activities related to customer services, one of which is citizen complaints. The measurement will compare the actions and steps taken during the processing of citizen complaints to the guidelines developed and adopted to process citizen complaints. Requirement: Chapter 880-X-11B of the Rules of the Alabama Surface Mining Commission outlines ASMC's procedures for receiving and acting on requests for inspection when there is reason to believe that certain violations, conditions or practices exist. These procedures address confidentiality of the citizen, the determination of reason to believe, access to the permit site, the accompanying citizen, timing of action taken, response to the citizen, and the citizen's right to appeal the action taken. Background: REG-8 requires the Field Office to evaluate the effectiveness of customer service each evaluation year. The BFO has selected this area of State activities to review to determine timeliness, accuracy, completeness and appropriateness of State action. The BFO has not recently conducted a review in citizen's complaints. Because of OSM's emphasis on public participation, the BFO needs to develop a better understanding of ASMC's citizen complaint processes in the areas of initial action and subsequent follow-up action and notifications. The BFO particularly needs a better understanding of follow-up actions taken on citizen complaints received by OSM and forwarded to ASMC through the TDN process. Population/Sample:The population will be those citizen complaints received during the period of October 1, 1996 through September 30, 1997. This includes those complaints received directly by ASMC and those provided to ASMC by the BFO through the TDN process. A sample of approximately 20 will be selected for this review. Summary of Planned Review: The BFO will coordinate each phase of the review with designated ASMC personnel. Discussions will be conducted with appropriate ASMC personnel to identify procedures and guidance for receiving and documenting citizen complaints. The review will address the nature of the complaint, the manner of receipt, action taken, and citizen notification. Also addressed will be the time frame of the procedures and the general outcome of the complaints processed by ASMC during review period. Reporting: A report will be prepared addressing the scope, method, and the time frame of the review. This report will identify the documents reviewed and the sample of citizen complaints reviewed. It will also highlight the findings and recommendations. A draft copy of this report will be provided to ASMC for comment before finalizing. Schedule: Develop a review Sample, and commence by March 1, 1998. Complete data collection by July 1, 1998 Prepare a draft report by July 15, 1998. ASMC will be afforded 30 days to provide comment to the BFO ASMC comments will be incorporated, and the final report will be prepared by August 20, 1998.

ALABAMA ENHANCEMENT AND PERFORMANCE REVIEW EVALUATION YEAR 1998 Principle Being Evaluated: Acid Mine Drainage Reason for Selection: This area is considered for review in order to evaluate the Regulatory Authority performance relative to inspection activities and procedural compliance on sites with actual or potential acid mine drainage problems. Requirements: Chapter 880-X-10-C of the Rules of the Alabama Surface Mining Commission requires that surface mining activities be conducted according to approved plans to minimize acidic, toxic or other harmful infiltration of ground and surface water. Acid-forming and toxic-forming spoil is to be identified, buried, or otherwise treated to avoid contamination of the ground and surface water. Ground and surface water are to be monitored for early identification of acidic or toxic infiltration. Background: A study was recently completed on the permitting requirements for identification and subsequent handling of toxic materials. That follow-up review dealt with the technical aspects of identifying, isolating and treating toxic or acidic materials. This review is intended to evaluate routine inspection activities involving mine sites identified as potential AMD producers. The review is to determine coordination between the permitting/technical staff and the inspector, compliance with AMD policies and procedures by the permittee, the permitting staff, and the inspector. Further, it is to identify the course of actions when new AMD concerns are identified on an existing permit. Population/Sample: The population will include active permits issued prior to September 30, 1997. The sample (approximately 20) will be drawn from permits with identified potential AMD problems. Summary of Planned Review: Each phase of the review will be coordinated with designated ASMC personnel. BFO personnel will initiate discussions with ASMC technical staff and inspectors to identify existing policies and guidance. Once the sample is selected, BFO personnel will review the selected permit files and will conduct field reviews of the selected sites. With each permit, continued discussions will be conducted with the inspector in order to determine the trail of AMD actions or events and compliance activities, including adherence to the toxic materials handling plan. Reporting: A report will be prepared addressing the scope and method of the review, the time frame, samples evaluated, documents reviewed, and the findings and recommendations. A draft copy will be provided to ASMC for their review and comment prior to finalizing the report. Schedule: Develop and inspection sample, and begin the review by March 1, 1998. Complete collection of data by July 1, 1998. Prepare a draft report by July 15, 1998. ASMC will be afforded 30 days to provide written comment to the BFO. ASMC comments will be incorporated, and the final report will be prepared by August 30, 1998.